API 11S6 : 1995
API 11S6 : 1995
RECOMMENDED PRACTICE FOR TESTING OF ELECTRIC SUBMERSIBLE PUMP CABLE SYSTEMS
American Petroleum Institute
RECOMMENDED PRACTICE FOR TESTING OF ELECTRIC SUBMERSIBLE PUMP CABLE SYSTEMS
American Petroleum Institute
1 SCOPE
1.1 General
1.2 Organization
1.3 Jurisdiction
2 DEFINITIONS
2.1 AC Tests
2.2 Acceptance Testing
2.3 Conductor Resistance
2.4 Connectors
2.5 DC Tests
2.6 Diagnostic Testing
2.7 Grounding Stick (Discharge Resistor)
2.8 High Potential (HI-Pot) Tests
2.9 Insulation Conductance
2.10 Insulation Impedance
2.11 Insulation Resistance
2.12 IR Tests
2.13 Leakage Current
2.14 In-Situ Testing
2.15 Megohmmeter Tests
2.16 Penetrators
2.17 Potheads
2.18 Power Factor
2.19 Maintenance Testing
2.20 Time Domain Reflectometer (TDR)
3 INSULATION PROPERTIES
3.1 Description
3.2 Application
3.3 Limitations
3.4 Procedure
4 SAFETY
4.1 Description
4.2 Application
4.3 Procedures
5 VISUAL INSPECTION
5.1 Description
5.2 Application
5.3 Limitations
5.4 Procedure
5.4.1 Armor
5.4.2 Jacket
5.4.3 Insulation Coverings
5.4.4 Insulation
5.4.5 Conductors
5.4.6 Motor Lead Extension/Pothead
5.4.7 Connecting Devices
6 CABLE SYSTEM PREPARATION
6.1 Description
6.2 Application
6.3 Limitations
6.4 Procedure
6.4.1 Cable With Connecting Devices
6.4.2 Cable Without Connecting Devices
7 ACCEPTANCE TESTING
7.1 Description
7.2 Application
7.3 Limitations
8 MAINTENANCE (PROOF) TESTING
8.1 Description
8.2 Application
8.3 Limitations
9 IN-SITU TESTING
9.1 Description
9.2 Application
9.3 Limitations
10 DIAGNOSTIC (FAULT) TESTING
10.1 Description
10.2 Application
10.3 Limitations
11 INSULATION RESISTANCE (MEGOHMMETER) TESTS
11.1 Description
11.2 Application
11.3 Limitations
11.4 Test Procedure
12 DC HIGH POTENTIAL TESTS
12.1 Description
12.2 Application
12.3 Limitations
12.4 Test Procedure
13 AC TESTING
13.1 Description
13.2 Application
13.3 Limitations
14 FAULT LOCATION TESTS
14.1 Murry LOOP (Bridge Fault Locator) Tests
14.1.1 Description
14.1.2 Application
14.1.3 Limitations
14.1.4 Procedure
14.2 Capacitive Discharge Instrument (Thumper)
14.2.1 Description
14.2.2 Application
14.2.3 Limitations
14.2.4 Procedure
14.3 Time Domain Reflectometer (TDR) Tests
14.3.1 Description
14.3.2 Application
14.3.3 Limitations
14.3.4 Test Procedures
Covers testing of Electric Submersible Pump Cable Systems. Cable testing, in general, can be broken into three basic categories: The first category provides general definitions and an overview of terms, safety considerations and cable system preparation guidelines. The second identifies various situations under which testing takes place. The third category covers methods of testing and procedures.
Document Type | Standard |
Status | Current |
Publisher | American Petroleum Institute |
ProductNote | Reconfirmed 1995 |